Mezzanine Finance
Mezzanine finance is a second-charge layer of development funding that sits behind your senior lender and in front of your own equity, used to close the gap between what the senior facility will advance and what the scheme actually costs. A senior lender stopping at 65–70% of cost leaves a developer finding 30–35% in cash; mezzanine takes the combined position to around 85–90% of cost and 70–75% of gross development value, cutting the cash you put in to roughly 10–15%. It is priced well above senior debt — typically 1.2–2% per month, or a fixed share of profit — because the mezzanine lender is repaid only after the senior debt clears. Used well, it is the difference between running one scheme and running three.
Criteria and pricing
What lenders on our panel will typically do on this product today.
- Combined loan to cost
- Up to 85–90% including senior debt
- Combined loan to GDV
- Typically capped at 70–75%
- Rate
- From ~1.2% pcm rolled; profit-share structures also available
- Typical facility size
- £250,000 to £10m+
- Term
- 9–30 months, aligned to the senior facility
- Arrangement fee
- 2%+, plus an exit fee on many structures
- Security
- Second charge, intercreditor deed with the senior lender, personal guarantee
- Minimum developer equity
- Usually 10% of total cost, genuinely cash
- Profit on cost required
- 20%+ after all finance costs
Worked example — £4m GDV residential scheme
- Total cost (land plus build)
- £2,800,000
- Gross development value
- £4,000,000
- Senior debt at 65% of cost
- £1,820,000
- Equity gap before mezzanine
- £980,000
- Mezzanine at 1.4% pcm, 18 months
- £700,000
- Developer cash required
- £280,000 (10% of cost)
- Combined loan to cost
- 90%
- Combined loan to GDV
- 63%
- Mezzanine cost including fees
- ≈ £215,000
Figures are typical UK market ranges as at 2026 and are indicative only — your terms depend on the asset, the exit and the lender we place the case with.
Who this works for — and who it does not
You are likely to qualify if
- A senior development facility agreed or agreeable in principle — mezzanine is never the first call
- At least two comparable completed schemes, or a main contractor and project manager who have
- Profit on cost of 20% or more after the mezzanine cost is deducted, not before
- Genuine cash equity of around 10% of total cost; vendor deferral rarely counts
- A senior lender willing to sign an intercreditor deed
This is the wrong product if
- First-time developers — the risk sits second in line and lenders price experience, not optimism
- Schemes where the margin only works if values rise during the build
- Borrowers looking to take cash out at drawdown rather than fund construction
- Cases where the senior lender refuses a second charge, which some clearing banks do as policy
What actually happens, and when
- Day 0–2
Appraisal review
We stress the appraisal at a 10% GDV fall and a 10% cost overrun. If profit on cost survives that at 20%, the case is fundable; if it does not, mezzanine makes the scheme worse, not better.
- Day 3–7
Senior alignment
Terms are negotiated alongside the senior lender so the two facilities share one drawdown schedule and one monitoring surveyor.
- Week 2–4
Intercreditor and legals
The intercreditor deed between the two lenders is the long pole. Starting it late is the most common cause of a delayed start on site.
- Week 4–6
Drawdown
Both facilities complete together and the first drawdown is released against the surveyor's initial report.
