Commercial and mixed use

Mixed Use Development Finance

Mixed use development finance funds schemes combining residential with commercial floorspace — flats over shops, offices with apartments above, or larger regeneration blocks — to 60%–65% of gross development value and up to 90% of cost, at roughly 7%–11% per year. The complication is not the funding structure but the valuation: the residential element is valued on comparables and the commercial on yield, so lenders will discount unlet commercial space heavily and may assume a bulk sale on the flats. Schemes where the commercial floorspace is pre-let, or deliberately kept small, get materially better terms than schemes carrying speculative retail.

At a glance

Criteria and pricing

What lenders on our panel will typically do on this product today.

Loan to GDV
Up to 65%; 60% where commercial exceeds 30% of GDV
Loan to cost
Up to 90%, including 100% of build costs
Rate
7% – 11% per year, rolled
Loan size
£500,000 – £30m
Term
12 – 30 months
Arrangement fee
1.5% – 2%; exit fee 1% – 2%
Commercial element
Pre-let preferred; speculative space valued cautiously
Drawdowns
Monthly in arrears against monitoring surveyor sign-off
Exit
Unit sales, investment refinance, or a combination
Worked example

Worked example — 12 flats over two retail units

Site purchase
£950,000
Build cost
£2,750,000
Total cost with fees and finance
£4,150,000
Residential GDV (12 units)
£4,200,000
Commercial GDV (two units, one pre-let)
£1,150,000
Total GDV
£5,350,000
Facility at 63% LTGDV
£3,370,000
Developer equity
≈ £780,000
Exit
Flats sold; retail retained and refinanced onto a commercial mortgage

Figures are typical UK market ranges as at 2026 and are indicative only — your terms depend on the scheme, the exit and the lender we place the case with.

Honest fit

Who this works for — and who it does not

You are likely to qualify if

  • Detailed planning consent for the mixed scheme as drawn
  • A build contract with a contractor experienced in the relevant construction type
  • Two prior comparable schemes delivered by the developer or the appointed team
  • Equity of 10%–20% of total cost committed ahead of the first drawdown
  • A commercial letting strategy, or an accepted assumption of a discounted bulk sale

This is the wrong product if

  • Schemes where speculative retail makes up the majority of the value
  • Sites held on an option or subject to unresolved planning conditions
  • Developers with no delivery history on comparable construction
  • Appraisals where profit on cost falls below roughly 15% before contingency
Timescales

What actually happens, and when

  1. Week 1

    Appraisal review

    We separate residential and commercial value, test the yield assumption on the commercial element and confirm the scheme still works if the retail lets slowly.

  2. Week 1–2

    Terms

    Terms from lenders that genuinely underwrite mixed use — many development desks are residential-only in practice, whatever the brochure says.

  3. Week 3–5

    Valuation and QS

    Red Book valuation on both elements, plus an initial QS report on costs, programme and contingency.

  4. Week 6–8

    First drawdown

    Legals complete, land funded, and build drawdowns begin monthly in arrears.

Questions

Frequently asked

Next step

Request indicative terms

Four details are all a lender needs to price a case: how much, what secures it, when you need it and how it is repaid. Send those and we come back with realistic terms — or tell you plainly that the case will not place.

Request indicative terms

Tell us the four things every lender asks first. We come back with realistic terms, usually the same working day.

No obligation, no credit search at this stage. We reply with realistic terms or tell you plainly that we cannot place it.